Installation Overview

The Labcyte Echo Liquid Handler is installed by Labcyte field engineers. The following is a brief overview of the hardware and
software installation steps they perform:
1. Unpack the Echo Liquid Handler and place it in the area that meets the minimum operating space requirement.
2. Connect the Echo Liquid Handler to AC power, air pressure, vacuum pressure, surge tank, coupling fluid bottle, and the
coupling fluid chiller.
3. Fill the coupling fluid bottle and prime the coupling fluid circuit.
4. Perform a basic functional check of the Echo Liquid Handler.
5. Perform the Site Acceptance Test (SAT) process (optional).
6. Change the Echo IP address, if a different IP address is required by your system administrator.
7. Install the Echo Liquid Handler software onto the customer-supplied PC (client workstation).
8. Connect the client PC to the Echo Liquid Handler and verify communications.
Figure 35: Installed system
Note: The surge tank is included with the Echo but not required. The surge tank should be used when the house
vacuum does not support the volumetric flow required by the Echo.