Note: Do not connect the MGMT 10/100 Ethernet port to the LAN until the initial
switch configuration has been performed. For instructions on configuring the
switch, see the Cisco NX-OS Fundamentals Configuration Guide.
For instructions on connecting to the console port, see "Connecting to the Console
Port" on page 91.
To verify hardware operation, follow these steps:
Procedure
1. Verify that the face plates of all modules are flush with the front of the chassis,
2. Verify that any empty module slots have filler panels installed.
3. Verify that power supplies and the fan module are installed.
4. Check the power cable retainer of the power supplies, captive screws of fan
5. Ensure that the switch is adequately grounded as described in "System
6. Power on the switch by turning the power switches on the power supplies or

Powering Up the Switch

Before you begin
Complete the steps in "Verifying Component Installation" on page 87 before
powering up the switch.
About this task
To power up the switch, follow these steps:
Procedure
1. Power on the switch by turning the power switches on the power supplies or
2. Listen for the fans; they should begin operating as soon as the switch is
3. After the switch has finished booting, verify that the LED operations is as
88
SAN192C-6, SAN384C-6 and SAN768C-6 Installation, Service, and User Guide
and the ejector levers are fully closed and approximately parallel to the
faceplate of the module.
module, and all supervisor, switching, or services modules, and tighten any
retaining screws to specification.
Grounding" on page 71, and that the power cables are connected to outlets that
have the required AC or DC power voltages. See Appendix A, "Product
Specifications," on page 99, for the required voltages.
PEMs to the on (|) position or restoring power to the DC circuit, as required.
The switch boots automatically.
PEMs to the on (|) position or restoring power to the DC circuit, as required.
The switch boots automatically.
powered on.
CAUTION:
Do not operate the switch without a functioning fan module except during
the brief fan module replacement procedure. The IBM c-type SAN switches
and devices can operate for only a few minutes without a functioning fan
module before they begin to overheat.
follows:
v Fan module Status LED is green.
v Power supplies:
– Input OK LED is IN.