Figure 13
shows the restraint brackets and bolt installation dimensions for the system cabinet.
Figure 13: Seismic system cabinet restraints
Figure 14
shows how a floor mounting bracket is installed. Keithley part numbers are included for the required
hardware.
Figure 14: Floor mounting bracket installation

Equipment startup

All of the instruments in the equipment rack are connected to one power distribution unit (PDU), which is located at
the back of the cabinet.
Check that all line cords for the system cabinet are connected to AC power line receptacles.
Make sure the PDU circuit breaker on the back of the cabinet is in the ON position (see
circuit breaker is tripped, turn it OFF and then turn it back ON.
24
Figure
15). If the
PA-992 Rev. D / April 2012