The Check 1, Check 2 and Check 3 procedures on
CHECK 1
Check on connector of fan motor (Power supply cable)
1 . Turn off the power supply .
Measure the resistance between phases of U,V,W at the
motor side connectors (three-core wire) to check that
the values are balanced and there is no short circuiting,
while connector or relay connector is disconnected .
CHECK 2
1 . Turn off the power supply .
2 . Measure the resistance between Vcc and each phase
of U, V, W, and GND and each phase at the motor side
connectors (five-core wire) to check that the values are
balanced within the range of ± 20 %, while connector or
relay connector is disconnected . Furthermore, to use a
multiple meter for measurement, connect the probe of
negative pole to Vcc and that of positive pole to GND .
OM 1141-3 • MICROTECH UNIT CONTROLLER
page 128 and 129
are used to troubleshoot many error codes .