Installation Of The Supply Line In The Termination Panel - Sirona TENEO Installation Requirements

Dental treatment center
Hide thumbs Also See for TENEO:
Table of Contents

Advertisement

3 Installation of the supply lines
Underfloor installation of supply lines
12
1
Water supply
Pipe 10x1 mm, corner valve outlet 3/8"
2
Compressed air supply
Pipe 10x1 mm, corner valve outlet 3/8"
3
Suction line
DN40 HT-PP DIN 19 560 (polypropylene, inner diameter
36.5 mm)
4
Water drainage
DN40 HT-PP DIN 19 560 (polypropylene, inner diameter
36.5 mm)
5
Installation pipe
DN40 HT-PP DIN 19 560 (polypropylene, 40 mm)
6
Control line for the suction machine and call line
2
3X1.5 mm
7
Power supply
2
3x1.5 mm
Circuit breaker: for 230 VAC: 16 A slow-blow
for 100-115 VAC: 20 A slow-blow
Recommended: Type B automatic circuit breaker
8
Not applicable
9
Installation pipe
(or corresponding flat conduit) for the PC connection
3.3.2
Installation of the supply line in the termination
panel
✔ An installation template is available or was prepared.
1. Check the position of the supply lines against the installation template as
per the practice blueprint. Ensure that sufficient space is provided
between the lines and the walls; see "Scale 1:20" [ 17]. The center of the
hole in the floor must be 268 mm (10 1/2") from the foot of the treatment
center.
2. Lay the ends of the supply pipes, corner valves and lines as shown in the
illustrations.
The top edge of the corner valves for air and water must not project more
than 60 mm from the top edge of the floor.
The suction and drainage pipes must be flush with the top edge of the
floor (a deviation of +5 mm is permissible). The inner diameter of both
pipes is 36.5 mm.
The electric lines must project by at least 500 mm.
The supply lines are laid.
Sirona Dental Systems GmbH
Installation Requirements TENEO
61 93 739 D3509
D3509.021.01.04.02 04.2009

Advertisement

Table of Contents
loading

Table of Contents