1MRK 504 165-UUS -
Transformer protection RET670 2.2 ANSI
Commissioning manual
1.
Right click on the IED in the plant structure and select Signal Monitoring.
2.
Click on the List View tab.
3.
Click Forcing Session in the menu IED/Start Forcing.
IEC15000023 V1 EN
4.
Click Start editing signal value for forcing on the tool bar.
IEC15000024 V1 EN
The Signal Monitoring menu changes and indicates the forcing values that can be
edited.
IEC15000025 V1 EN
5.
Select and edit the values.
6.
Click Acknowledge and send.