C Transport And Commissioning; Lifting By Crane - Jungheinrich EKS 110 Operating Instructions Manual

For order picking processes from the first to the third racking levels
Hide thumbs Also See for EKS 110:
Table of Contents

Advertisement

C Transport and Commissioning

1

Lifting by crane

F
Only
use
sufficient capacity
(For weight lifted see truck data
plate).
Z
Strapping points for lifting the
truck with crane are provided on
the chassis (1 + 2).
– Park the truck securely (See
Chapter E).
– Attach the crane slings to the
strap points (1) and (2).
Attach the crane slings to the
strap points so that they cannot
slip and do not touch any
attachments during lifting.
lifting
gear
with
1
2
C 1

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents