C Transportation and commissioning

1

Loading and unloading of trucks by crane

F
Ensure that the lifting gear is of adequate capacity.
(Transportation weight = net weight + battery weight; see truck identification plate)
– To load the truck with lifting gear, lay the loop of the rope around the strut of the
overhead guard (1). Two lifting points (2) are provided on the wheel arms.
– Park the truck and render it safe (refer to chapter E).
– Use chocks to prevent the truck from moving!
M
The lilting gear must be secured to the lifting points in such a way that it does not
come into contact with any attachments when the truck is lifted.
2

Commissioning

M
The truck must only be operated on battery current. Rectified alternate current will da-
mage the electronics. Cables connected to the battery (towing cable) must be less
than 6 meters in length.
To prepare the truck for work following delivery or transportation, the following ope-
rations must be performed:
– Check that the equipment is complete.
– If necessary, install the battery. Do not damage the battery cable (refer to chapter
D).
– Charge the battery (refer to chapter D).
– Commission the truck as prescribed (refer to chapter E).