If some setting deviates, check the analog input settings under
Main menu/Settings/General settings/Analog modules
Testing the protection functionality
Each protection function must be tested individually by secondary injection.
•
Verify operating levels (trip) and timers.
•
Verify alarm and blocking signals.
•
Use the disturbance handling tool in PCM600 to evaluate that the protection
function has received the correct data and responded correctly (signaling and
timing).
•
Use the event viewer tool in PCM600 to check that only expected events have
occurred.