ABB REG670 2.0 IEC Commissioning Manual page 143

Relion 670 series generator protection
Table of Contents

Advertisement

1MRK502053-UEN B
Generator protection REG670 2.0 IEC
Commissioning manual
Testing functionality by secondary injection
frequency of V
= 50 Hz
ts
I
= 0 A
50s
I
= 0 A
tfs
State 2: main test step.
Define the following three-phase symmetrical quantities (the phase angle is
related to phase L1):
V
VT s
,
V
0 9
.
V
=
×
×
ts
t RvsZ
,
V
VT p
,
EQUATION14067 V1 EN
æ
ReverseX
Ð
=
ç
V
arctan
è
ts
ReverseR
EQUATION14068 V1 EN
frequency of V
= 50 Hz
ts
I
CTs
I
I
10459
=
×
=
50
s
50
I
CTp
EQUATION14059 V1 EN
∠I
= 0º
50s
frequency of I
= 50 Hz
50s
I
CTs
It
I
10459
=
×
=
tf
fs
I
CTp
EQUATION14062 V1 EN
∠I
= 180º
tfs
frequency of I
= 50.5 Hz
tfs
Expected result: start of the protection function and trip in zone 1 when trip
conditions are fulfilled.
The trajectory of the impedance does not enter the lens characteristic
Preliminary steady state test at 50 Hz
Go to Main menu/Test/Function status/Impedance protection/
OutOfStep(78,Ucos)/OOSPPAM(78,Ucos):1/Outputs to check the available
service values of the function block OOSPPAM.
Apply the following three-phase symmetrical quantities (the phase angle is
related to phase L1):
V
VT s
,
V
1 1
.
V
=
×
×
ts
t RvsZ
,
V
VT p
,
EQUATION14069 V1 EN
0 1
.
0 9 5899
.
38 47
.
=
×
×
=
13 8
.
ö
æ
29.60
-
° =
÷
ç
180
arctan
ø
è
0.29
1
= .
1 162
A
×
9000
1
1 162
.
A
×
=
9000
0 1
.
1 1 5899
.
47 02
.
=
×
×
=
13 8
.
Section 12
V
ö
-
° = -
°
÷
180
90.56
ø
V
(Equation 63)
(Equation 64)
(Equation 65)
(Equation 66)
(Equation 67)
137