Completing The Test; Fuse Failure Supervision Fufspvc; Checking That The Binary Inputs And Outputs Operate As Expected - ABB REG670 2.0 IEC Commissioning Manual

Relion 670 series generator protection
Table of Contents

Advertisement

1MRK502053-UEN B
12.9.1.2
12.9.2
12.9.2.1
Generator protection REG670 2.0 IEC
Commissioning manual
Testing functionality by secondary injection

Completing the test

Continue to test another function or end the test by changing the TestMode setting to
Off. Restore connections and settings to their original values, if they were changed for
testing purposes.

Fuse failure supervision FUFSPVC

Prepare the IED for verification of settings outlined in section
section
"Preparing for test"
The verification is divided in two main parts. The first part is common to all fuse
failure supervision options, and checks that binary inputs and outputs operate as
expected according to actual configuration. In the second part the relevant set operate
values are measured.

Checking that the binary inputs and outputs operate as expected

1.
Simulate normal operating conditions with the three-phase currents in phase
with their corresponding phase voltages and with all of them equal to their rated
values.
2.
Connect the nominal dc voltage to the DISCPOS binary input.
The signal BLKU should appear with almost no time delay.
The signals BLKZ and 3PH should not appear on the IED.
Only the distance protection function can operate.
Undervoltage-dependent functions must not operate.
3.
Disconnect the dc voltage from the DISCPOS binary input terminal.
4.
Connect the nominal dc voltage to the MCBOP binary input.
The BLKUand BLKZ signals should appear without any time delay.
All undervoltage-dependent functions must be blocked.
5.
Disconnect the dc voltage from the MCBOP binary input terminal.
6.
Disconnect one of the phase voltages and observe the logical output signals on
the binary outputs of the IED.
BLKU and BLKZ signals should appear simultaneously wether the BLKU and
BLKZ reset depends on the setting SealIn "on" or "off". If "on" no reset, if "off"
reset.
7.
After more than 5 seconds disconnect the remaining two-phase voltages and all
three currents.
There should be no change in the high status of the output signals BLKU
and BLKZ.
The signal 3PH will appear.
8.
Establish normal voltage and current operating conditions simultaneously and
observe the corresponding output signals.
They should change to logical 0 as follows:
in this chapter.
Section 12
"Requirements"
and
197