Grounding The Switch; Figure 7: Status Leds 5 Minutes After Power On - Mellanox Technologies switchx MSX1035B-1BRR Installation Manual

36 port qsfp ethernet switch
Table of Contents

Advertisement

Rev 1.4
9.
Slide the switch into the rails.
10. Tighten the bolts to 9.2 Nm or 81.5 pound inches.
11.
Put the switch into place and screw the bolts into the nuts. Tighten the bolts to 9.2 Nm or
81.5 pound inches.
12. Ground the switch.
13. Plug in the power cables.
14. Check the Status LEDs and confirm that all of the LEDs show status lights consistent with
normal operation.
15. You can start connecting all of the cables to the switch.

1.3.2 Grounding the Switch

Check to determine if your local or national electrical codes require an external ground to all IT
components. If so, connect a ground wire to one of the casing screws and connect the other end to
a valid ground. If you choose to not use the ground screw, make sure that the rack is properly
14
Mellanox Technologies

Figure 7: Status LEDs 5 Minutes After Power On

Warning: Any yellow or red status LEDs are cause for concern and must be dealt with
immediately.
It can take up to 5 minutes to boot up, during which time the status LED may indicate
red.
FDR and FDR10 are only guaranteed to work with approved Mellanox Cables.
Caution: Slide/rail mounted equipment is not to be used as a shelf or a work space.
Installing the Switch in the Rack