Agilent Technologies 5975 Operation Manual page 48

Series msd
Hide thumbs Also See for 5975:
Table of Contents

Advertisement

2
Installing GC Columns
Figure 10
7 Loosen the interface nut and push the column an additional 3–5 cm into
8 Make a clean cut of the column so that now only 3–5 cm protrudes into the
9 Clean the outside of the free end of the column with a lint-free cloth
10 Adjust the column so that it protrudes 1 to 2 mm into the analyzer chamber
48
22–28 cm from 3 o'clock clip to GC/MSD interface nut
Oven door opened and closed
the analyzer chamber.
analyzer chamber.
moistened with methanol.
past the end of the GC/MSD interface, and hand tighten the nut. See
Figure
11.
Make sure the position of the column does not change as you retighten the
nut.
5975 Series MSD Operation Manual for MassHunter

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents