Figure 5-5 Cage Nuts location options in a Rack Post
11.
Repeat the same procedure for the right front rack post making sure that the
cage nut is at the same height as the left side.
5.2.3.4
Mounting the Library in the Rack
THE RLS WEIGHS UP TO 174 LBS (79 KG) ), INCLUDING STORAGE MATRICES
AND TAPE DRIVES AND A MINIMUM OF TWO PEOPLE ARE NEEDED TO LIFT IT.
HANDLING THE RLS ALONE COULD RESULT IN BACK INJURY OR OTHER
ACCIDENTS.
1.
If powered, remove power from the RLS by first pressing the power switch off
and then removing the power cord.
2.
If the storage matrices have not already been removed from the library, follow
the procedure described in Section 5.7.5 to remove them.
3.
If any tape drives are in the library, follow the procedure described in Section
5.5.2 to remove them.
4.
Have two or more people lift the library by grabbing the front and rear hand
holds as seen in Figure 5-6. Place it between the rack posts and slide it back on
the rack rails until about 8 inches remains sticking out the front of the rack
posts.
5-6
4 Cage Nut
Location Options
DANGER
Installation
511000 Rev. F

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Rls-85 series

Table of Contents