Installing the boiler on a boiler base
or foundation
When setting up the boiler, we recommend you observe
the specified wall clearances for improved installation and
maintenance (Fig. 5).
It is advisable to place the boiler on a 2 – 4 inch
(50 – 80 mm) tall base (Fig. 6, [1]). The base should be
completely flat and level. The front edge of the boiler
should be flush with the edge of the base.
A silencing boiler base is available as
optional equipment from Buderus.
If this optional boiler base is not used, a concrete
foundation can be constructed on-site. When building the
foundation, a 3 15/16 x 1 31/32 x 5/16 inches
(100 x 50 x 8 mm) steel angle or 3 15/16 x 13/64 inches
(100 x 5 mm) steel flat should be incorporated (
and Tab. 9).
34-3/4"
34 3/4"
(~ 880 mm)
4"
(100 mm)
21 1/4"
(540 mm)
Fig. 6
Base dimensions
Logano G315 - Subject to technical modifications
Number of
boiler sections
Tab. 9 Foundation dimensions and lengths of steel flats
Fig. 6
1
6 720 642 621-01.1o
Positioning the boiler
L1
(base)
in inch (mm)
5
38-3/16 (970)
6
44-31/64 (1130)
7
50-25/32 (1290)
8
57-3/32 (1450)
9
63-25/64 (1610)
or steel angles
6
L2
(steel section)
in inch (mm)
28-3/4 (730)
35-1/32 (890)
41-21/64 (1050)
47-41/64 (1210)
53-15/16 (1370)