Boiler Foundation And Minimum Boiler Clearances - Buderus G315 Assembly, Maintenance And Operating Instruction

Table of Contents

Advertisement

4 Boiler Foundation and Minimum Boiler Clearances

Boiler foundation preparations
It is required that the boiler is placed on a level, smooth
concrete base, of sufficient strength. The width of the
platform must be 33 1/2". Length L 1 is the platform
length. It is required to cement in either a 4" x 1/4" flat
steel plate or a 4" x 2" x 1/4" angle iron, as shown in
Figure 2; Table 3 shows dimensions.
Table 3: Foundation and support strip lengths
No. of Sections Length LI (In.)
5
36
1 /4
6
42
1 /2
7
48
3 /4
8
54
9
61
Minimum wall clearances
The recommended wall clearances must be observed in
order to open the burner door, assemble the boiler and
allow sufficient access for boiler maintenance.
(See Figures 3 and 4 for details).
The burner door is field adjustable to hinge right or left.
Recommended clearances:
Wall clearance W1: minimum 12".
Wall clearance W2: Burner length A + 4", minimum 43".
Wall clearance W3: Boiler length L + 40".
Wall clearance W4: 1/2 Boiler length + 20".
Absolute minimum clearances:
Wall clearance W1: minimum 12".
Wall clearance W2:* minimum 12".
Wall clearance W3: Boiler length L or minimum 86".
Wall clearance W4: 36".
Note:
Wall clearance W3 can be reduced to 4 feet for
assembled boilers. Boiler cleaning will now require
use of segmented brushes.
*Requires burner removal during cleaning.
6
Length L2 (In.)
3 /4
28
35
1 /4
41
1 /2
47
54
4 "
4 "
Fig. 2
Fig. 3
Fig. 4
33
"
1 / 2
10"
4 "
3
20"
7
"
3 / 4
7
"
3 / 4
16"
"
1 / 2

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents