Page 1
GE Digital Energy INSTALLATION / USER MANUAL UNINTERRUPTIBLE POWER SUPPLY LanPro 11 U 5/6/8/10 kVA Manufactured by: GE Digital Energy General Electric Company Telephone +41 (0)91 / 850 51 51 CH – 6595 Riazzino (Locarno) +41 (0)91 / 850 51 44...
Page 2
® LanPro -U is a registered trademark of GE Digital Energy. Trademarks of other companies used in this document are registered trademarks of their respective owners. LX: OPM_LPA_11U_5K0_10K_1US_V021...
5.5 Other Features 5.5.1 Shutdown 5.5.2 Mains start 5.5.3 Sleep and wake-up 5.5.4 Overload protection in bypass mode 5.5.5 ECO-Mode 5 5.6 Auto restart 5.5.7 Superior battery management LX: OPM_LPA_11U_5K0_10K_1US_V021 GE DE LanPro-11U UPS: Installation / User Manual 2.1 (US)
Page 4
7.6 120Vac Single Phase Option Kit MAINTENANCE ................. 37 8.1 General 8.2 Cooling fan 8.3 Batteries 8.4 Safety 8.5 Storage TROUBLESHOOTING ............... 38 SPECIFICATIONS..............39 APPENDIX: INSTALLATION DRAWINGS LX: OPM_LPA_11U_5K0_10K_1US_V021 GE DE LanPro-11U UPS: Installation / User Manual 2.1 (US)
CAUTION: By opening or removing covers you run the risk of exposure to dangerous voltages! While every care has been taken to ensure the completeness and accuracy of this manual, GE Digital Energy assumes no responsibility or liability for any loss or damage resulting from the use of the information contained in this document.
More than ever before, today's advanced electronic equipment, with complex integrated circuits and other sensitive electronics, needs a stable and continuous AC power supply to operate correctly. While the power coming from the ® wall outlet is often unreliable, a GE Digital Energy LanPro -U UPS provides the security of completely uninterrupted power.
RELAY CARD FRONT SYSTEM PANEL BATTERY ON/OFF std. installed: BATTERY RS232/ EXTENSION CONTACT INTERFACE MICRO-PROCESSOR CONTROL ® Figure 3. Block diagram of the LanPro -11U UPS, utility failure LX: OPM_LPA_11U_5K0_10K_1US_V021 GE DE LanPro-11U UPS: Installation / User Manual 2.1 (US)
The UPS may only be installed by trained personnel. The UPS must be grounded when in use: Connect the UPS to a single phase, three wire AC source equipped with an earth connection. LX: OPM_LPA_11U_5K0_10K_1US_V021 GE DE LanPro-11U UPS: Installation / User Manual 2.1 (US)
Page 10
8 AWG 8 AWG Table 3. Output wiring TIGHTENING TORQUE FORCE: UPS model Tightening torque force L5/6-11U/120V 22 Lbs/inch All other models 18-20 Lbs/inch Table 4. Tightening torque force LX: OPM_LPA_11U_5K0_10K_1US_V021 GE DE LanPro-11U UPS: Installation / User Manual 2.1 (US)
(208Vac), software modifications should be performed as see 4.4.6 / 7.3 well. Proceed with 4.4.4. ® Figure 6. LanPro 5/68/10-11U: 12. For a quick start proceed with section 5.2 ‘Start-up’. Standard installation procedure LX: OPM_LPA_11U_5K0_10K_1US_V021 GE DE LanPro-11U UPS: Installation / User Manual 2.1 (US)
Page 12
(208Vac), software modifications should be performed as well. Proceed with 4.4.4. ® Figure 7. LanPro 5/6-11U: Installation procedure 120V input 12. For a quick start proceed with section 5.2 ‘Start-up’. LX: OPM_LPA_11U_5K0_10K_1US_V021 GE DE LanPro-11U UPS: Installation / User Manual 2.1 (US)
If a neutral wire is part of the site wiring provided, we suggest to isolate this wire for future use or other applications. Figure 9. LanPro 5/6/8/10-11U: Input/output terminals For the output voltage proceed with 4.4.3. LX: OPM_LPA_11U_5K0_10K_1US_V021 GE DE LanPro-11U UPS: Installation / User Manual 2.1 (US)
Connect the ground wire to terminal 5. Ground connection is essential! See figure 11. 208V ® Figure 11. LanPro 5/6/8/10-11U: 208 Vac output connection Return to either 4.4.1.1 step 5 or 4.4.1.2 step 5 LX: OPM_LPA_11U_5K0_10K_1US_V021 GE DE LanPro-11U UPS: Installation / User Manual 2.1 (US)
2 and 3. See figure 13. 120V 120V ® Figure 13. LanPro 5/6/8/10-11U: 120 Vac split-phase output connection Return to either 4.4.1.1 step 5 or 4.4.1.2 step 5 LX: OPM_LPA_11U_5K0_10K_1US_V021 GE DE LanPro-11U UPS: Installation / User Manual 2.1 (US)
Connect the load wires between connectors 1 (or 2) and 3(or 4). Return to either 4.4.1.1 step 5 or 4.4.1.2 step 5. 120 V ® Figure 15. LanPro 5/6/-11U: 120 Vac single phase output connection LX: OPM_LPA_11U_5K0_10K_1US_V021 GE DE LanPro-11U UPS: Installation / User Manual 2.1 (US)
To return to the default screen scroll to the setup screens first and press 'Enter/reset'. You can also wait 20 seconds: the time-out period of no key activity. You can now proceed with 5.1 or 5.2. LX: OPM_LPA_11U_5K0_10K_1US_V021 GE DE LanPro-11U UPS: Installation / User Manual 2.1 (US)
Page 18
300Vdc. NOTE: Third party battery cabinets must be connected over a 60Amp fuse, rated for 300Vdc, using the GE Digital Energy external battery cable (order separately). Insert the 2 (7Ah) or 4 (14Ah) DC fuses of the (each) battery pack, insert the DC fuses of the UPS and close the fuse holder(s) of battery pack and UPS (16).
NEUTRAL-TO-GROUND CABLES AS DELIVERED - MINIMUM 3 METERS / 9.8 FEET BOUNDING HERE WITH THE UPS TO LOAD ® Figure 17. Installation of parallel operating LanPro -U UPSs LX: OPM_LPA_11U_5K0_10K_1US_V021 GE DE LanPro-11U UPS: Installation / User Manual 2.1 (US)
If the parameters mentioned in 4.4.6.1 step 6 are not set to the same value the UPS will display the following screen after start-up: In this case check and correct the setting of the parameters as mentioned in 4.4.6.1, step 6. LX: OPM_LPA_11U_5K0_10K_1US_V021 GE DE LanPro-11U UPS: Installation / User Manual 2.1 (US)
To re-enter the unit into the system: 1. Reinstall the installation input fuse, 2. Connect the output of the UPS to the output junction, 3. Switch on the UPS. LX: OPM_LPA_11U_5K0_10K_1US_V021 GE DE LanPro-11U UPS: Installation / User Manual 2.1 (US)
Option slot for RPA (Redundant Parallel Architecture) Card. Not available yet. DC socket / connector. Battery fuse holder Conduit box Cable inlet Figure 19 : Front and rear panel LX: OPM_LPA_11U_5K0_10K_1US_V021 GE DE LanPro-11U UPS: Installation / User Manual 2.1 (US)
Page 23
DC connector 14Ah Battery fuse holder(s) 7Ah: 2 fuses 14Ah: 4 fuses Gland to fasten cable in conduit box of UPS Figure 21. Rear panel battery extension pack (optional) LX: OPM_LPA_11U_5K0_10K_1US_V021 GE DE LanPro-11U UPS: Installation / User Manual 2.1 (US)
® If not yet switched on, the equipment connected to the LanPro -U UPS can be switched on now; operate as usual. LX: OPM_LPA_11U_5K0_10K_1US_V021 GE DE LanPro-11U UPS: Installation / User Manual 2.1 (US)
The temperature near the batteries, the battery voltage and the battery current ° (charging: + value, discharging: - value). The remaining battery runtime (or autonomy) during a utility failure. The total operating time of the UPS. LX: OPM_LPA_11U_5K0_10K_1US_V021 GE DE LanPro-11U UPS: Installation / User Manual 2.1 (US)
The output voltage of the battery charger is too high, internal failure The battery temperature is too high due to a battery failure or a too high ambient temperature LX: OPM_LPA_11U_5K0_10K_1US_V021 GE DE LanPro-11U UPS: Installation / User Manual 2.1 (US)
Page 27
UPS (rectifier) input tolerance (see chapter 10, specifications). Bypass operation is inhibited: if for whatever reason the output converter is unable to deliver the required output, output power is lost. LX: OPM_LPA_11U_5K0_10K_1US_V021 GE DE LanPro-11U UPS: Installation / User Manual 2.1 (US)
Service information on internal temperature levels, values in mV over the temperature sensors. First line: service information on charger. ‘1’ = batteries have reached float voltage. Second line: service information on output converter. LX: OPM_LPA_11U_5K0_10K_1US_V021 GE DE LanPro-11U UPS: Installation / User Manual 2.1 (US)
Page 29
See also 4.5.5. Service set-up information about the autorestart function. This function can be switched on or off by pressing ‘ENTER/RESET’, depending on the actual status. See also 4.5.6. LX: OPM_LPA_11U_5K0_10K_1US_V021 GE DE LanPro-11U UPS: Installation / User Manual 2.1 (US)
NOTE: if the LanPro -U operates in parallel the no-load shutdown function is not available. In this case do not activate this function: its setting should read "NO". LX: OPM_LPA_11U_5K0_10K_1US_V021 GE DE LanPro-11U UPS: Installation / User Manual 2.1 (US)
NOTE: If the manual test is started immediately after installation or after a power failure, the UPS may generate a false 'replace battery' alarm as the batteries have been (partly) discharged during transport/storage or during the power failure. LX: OPM_LPA_11U_5K0_10K_1US_V021 GE DE LanPro-11U UPS: Installation / User Manual 2.1 (US)
The test has been completed succesfully The test could not be executed properly: not all test conditions were fulfilled. The UPS system was not informed about the actual battery condition! LX: OPM_LPA_11U_5K0_10K_1US_V021 GE DE LanPro-11U UPS: Installation / User Manual 2.1 (US)
'BATTERY DEPLETED' will be shown. The run time is zero. 5.5.3 Sleep and wake-up GE Digital Energy UPS monitoring software allows you to program a 'sleep period' of the UPS by sending two commands to the UPS: - shut down after # minutes, and subsequently: - shut down during # hours.
(-18mV/°C or -32.4mV/°F per 12V battery). As a result poor charging of the batteries under low temperature conditions and overcharging of the batteries under high temperature conditions are prevented. LX: OPM_LPA_11U_5K0_10K_1US_V021 GE DE LanPro-11U UPS: Installation / User Manual 2.1 (US)
When the utility power returns, the systems will automatically start up and will be up and running as soon as possible. For specific information on GE Digital Energy’s connectivity products please contact your dealer or internet: www.gedigitalenergy.com.
GE Digital Energy’s unique RPA system has the following major advantages: • GE Digital Energy’s RPA offers true redundancy because not only the power electronics are redundant, but also the batteries, the bypass circuit and the control logic, •...
120Vac Single Phase Option Kit This kit is required in case of 120Vac single phase output on 8/10kVA models This kit can be ordered separately; contact your local dealer. LX: OPM_LPA_11U_5K0_10K_1US_V021 GE DE LanPro-11U UPS: Installation / User Manual 2.1 (US)
-20 and +30°C (-4°F and 86°F): every 6 months, for 24 hours, if the storage temperature is within -20 and +45°C (-4°F and 113°F): every 4 months, for 24 hours. LX: OPM_LPA_11U_5K0_10K_1US_V021 GE DE LanPro-11U UPS: Installation / User Manual 2.1 (US)
UPS to save battery power. If the UPS input power is absent for several days and the UPS remains on under no- load conditions, the batteries can be discharged very deeply, resulting in a short battery life time. LX: OPM_LPA_11U_5K0_10K_1US_V021 GE DE LanPro-11U UPS: Installation / User Manual 2.1 (US)
Automatic shut down (or transfer to bypass, if bypass is available) in case of - low/high DC voltage - overtemperature - overload / short circuit The output is protected against connection to the utility supply * according to EN 50091-1 LX: OPM_LPA_11U_5K0_10K_1US_V021 GE DE LanPro-11U UPS: Installation / User Manual 2.1 (US)
Page 42
FCC part 15, class A; EN 50091-2 ENVIRONMENT Ambient temperature -10 to +40°C (14 to 104°F) Audible noise at 1 meter 40 - 50dB(A), the audible noise is load and temperature dependent LX: OPM_LPA_11U_5K0_10K_1US_V021 GE DE LanPro-11U UPS: Installation / User Manual 2.1 (US)
Page 43
VSD2: h x w x d 680 x 310 x 710 mm 26.8 x 12.2 x 28 Inch Front W= 155mm/ 6.1 Inch D= 300mm/ 11.8 Inch H= 275mm/ 10.8 Inch LX: OPM_LPA_11U_5K0_10K_1US_V021 GE DE LanPro-11U UPS: Installation / User Manual 2.1 (US)
Page 44
GE Digital Energy ® LanPro 5/6/8/10-11U installation drawings Model Heat dissipation Dimensions Weight Air flow Amb. Rel. Altitude Input wiring Output wiring Linear load 240 Volt 100% temp. humidity (max 4000m) load non-cond. 100% load 50% load utility volt. utility volt.
Page 45
GE Digital Energy ® LanPro 5/6/8/10-11U 208-240V input BATTERY FUSES MANUAL BYPASS SWITCH NORMAL: POSITION 1 (LOAD ON UPS) SERVICE: POSITION 2 (LOAD ON BYPASS) CONTROLS / CIRCUIT BREAKERS INPUT / OUTPUT TERMINALS STATIC UTILITY BYPASS L1 L2 EARTH CONNECTION...
Page 46
GE Digital Energy ® LanPro 5/6-11U 120V input BATTERY FUSES MANUAL BYPASS SWITCH NORMAL: POSITION 1 (LOAD ON UPS) SERVICE: POSITION 2 (LOAD ON BYPASS) CONTROLS / CIRCUIT BREAKERS INPUT / OUTPUT TERMINALS STATIC UTILITY BYPASS EARTH CONNECTION IS ESSENTIAL...