8. Mark and pre-drill the hole for the top mounting bolt (see
9. Remove the backbox.
10.In the top mounting hole, insert the mounting screw.
11.Tighten the screw, leaving space for hanging the enclosure.
12.Mount the backbox over the top screw and level it.
13.Mark the locations for the two lower mounting holes.
14.Remove the backbox and drill the mounting holes.
15.Mount the backbox over the top screw, then install the remaining fasteners.
16.Tighten all fasteners securely.
CLSS Gateway - Installation and Users' Manual | P/N:LS10248-000HW-E | REV. F | FEB/11/2022
Figure 4.2: Mounting the Backbox