Commissioning Tm54F By Means Of Starter/Scout; Basic Sequence Of Commissioning - Siemens SINAMICS G130 Manual

Safety integrated
Hide thumbs Also See for SINAMICS G130:
Table of Contents

Advertisement

8.5

Commissioning TM54F by means of STARTER/SCOUT

8.5.1

Basic sequence of commissioning

The following conditions must be met before you can configure the TM54F:
● Concluded initial commissioning of all drives
Table 8- 2
1
2
3
4
5
6
7
8
9
10
11
12
Safety Integrated
Function Manual, 05/2010, A5E03264275A
Configuration sequence
Step
Insert the TM54F
Configure the TM54F and generate the drive groups
Configure the drive groups
Configure the inputs
Configure the outputs
Copy the parameters to the second drive object (TM54F_SL)
Change the safety password
Activate the configuration by selecting "Activate settings"
Save the project in STARTER
Save the project in the drive by selecting "Copy RAM to ROM"
Execute POWER ON
Acceptance test
8.5 Commissioning TM54F by means of STARTER/SCOUT
Execution
Commissioning
199