System test procedure

Once the system is calibrated and setup, you should conduct a series of tests to
verify detection. Run a UCM Response plot during the testing. Network based
processors can be tested over the network to verify network communications.
Note:
The following tests can be used to verify FlexZone system operation. The
tests are described in a generic manner, which does not take into account site
specific details.
Cut detection -
Use the tap test, or weave a piece of scrap fence wire into the
fabric of the fence and cut the scrap wire. Test each zone in at least three
separate locations.
At each location, tap the fence fabric, or cut the scrap wire, the number of times
specified by the Event Count parameter. Wait at least 2 seconds between taps.
PASS ____
FAIL____
Climb detection -
Have a tester climb on the fence fabric for at least as long as
the Event Time X the Event Count (or use the screwdriver drag method). Repeat
the climb simulation in at least three locations per zone.
PASS ____
FAIL____
Fence lift detection (Use care to ensure that the fence is not damaged
during this test) -
minimum of the Event Time X the Event Count (depending on the amount of
fence noise being generated, the test may have to exceed the Event Time setting
by several seconds). Repeat the lift test in at least three locations per zone.
PASS ____
FAIL____
78
Have a tester lift or pry up the bottom the fence fabric for a