Manual Start - Eaton Powerware 9315 Installation And Operation Manual

Parallel capacity/redundant system
Hide thumbs Also See for Powerware 9315:
Table of Contents

Advertisement

10.3.2

Manual Start

1.
Perform the Initial Setup procedures.
2.
On SBM, turn the SYSTEM MODE key switch to BYPASS momentarily.
If a bypass source is available when you turn the SYSTEM MODE key switch to
BYPASS, the critical load is immediately supplied by the bypass source in Bypass
mode until the UPMs are available and the SBM has been manually transferred to
Normal mode. The status indicators on the SBM monitor screen indicate when the
Parallel Capacity/Redundant system
3.
Observe that CBP and FBP have closed.
4.
On first UPM, set BATTERY switch to ENABLE.
5.
On first UPM, turn the MODE key switch to NORMAL for three seconds.
6.
Confirm the UPS breaker CB1 has closed by verifying breaker position on LCD
mimic screen.
The rectifier and input/rectifier cooling fans blowers should be running.
7.
Confirm UPS Battery Breaker CB2 (MBB) has closed by viewing breaker
position on LCD Mimic screen.
NOTE: If CB2 is a manual battery breaker, manually close CB2 after UPM
The inverter and output/inverter cooling blowers turn on. When the inverter reaches
full voltage, UPS breaker CB3 closes. It takes less than 1 minute for the UPS to
achieve Normal mode. If UPS is not in Autorestart, turn the MODE key switch to
NORMAL for three seconds to transfer to Normal mode.
8.
UPS is now operating in Normal mode.
9.
Start remaining UPMs by repeating steps 4 through 8.
10.
On SBM monitor screen, check for On Bypass, UPMs Ready message.
11.
If message appears, turn the SBM SYSTEM MODE key switch to NORMAL
momentarily.
12.
Observe that breaker CBS closes, breaker CBP opens, and the SSW is turned
off.
EATON Powerware 9315 Parallel Capacity/Redundant System
164201150
Rev. E www.powerware.com
Battery Disconnected alarm and notification is received.
is in Bypass mode and Normal mode.
10−9