Getting Started

1.1

Installing the UPS

The System Bypass Module (SBM) and UPMs of the Parallel Capacity/Redundant
system are shipped on separate pallets. Use a forklift or pallet jack to move the
packaged cabinets to the installation site, or as close as possible to the site, before
unloading it from the pallet.
This is the basic sequence of the installation steps:
1.
Create an installation plan for the Parallel Capacity/Redundant system
(Chapter 1).
2.
Prepare your site for the Parallel Capacity/Redundant system (Chapter 1).
3.
Inspect, unpack, and unload the SBM (Chapter 1).
4.
Inspect, unpack, and unload the UPMs (refer to the applicable Powerware®
9315 Installation manual provided with the UPM).
5.
Wire the system (refer to Chapter 2 and the applicable Powerware® 9315
Installation manual provided with the UPM).
6.
Install features, accessories, and/or options, as applicable (Chapter 3).
7.
Complete the Installation Checklist (Chapter 2).
8.
Have authorized service personnel perform preliminary operational checks and
startup.
NOTE: Startup and operational checks should be performed only by authorized
service personnel. This service is usually offered as part of the sales
contract for your Parallel Capacity/Redundant system. Contact service
in advance (usually a two week notice is required) to reserve a preferred
startup date.
1.1.1

Creating an Installation Plan

Before beginning to install the Parallel Capacity/Redundant system, read and
understand how this manual applies to the system being installed. Use the
procedures and illustrations in the following chapters to create a logical plan for
installing the system. It is important to note that UPM installation procedures are
contained in the applicable Powerware® 9315 Installation manual provided with
the UPMs. First understand how to install the UPMs before installing the SBM.
The information in Chapter 2 of this manual is a guide to installation of the SBM to
the UPMs.