CONNECTING THE GAS SUPPLY
Firmly grasp the S/S flexi pipe
then attach pipe to gas control valve and tighten. To assist there is a small spanner, located in the pouch that
B
contains the commissioning instructions which is located on the top of the PCB cover
C
When the gas connection is completed, ensure that the spanner is returned to the commissioning
instruction pouch, so that it can be available for the next installer / service person.
IMPORTANT
LEAK TESTING
Turn gas back ON and leak test appliance connection.
Use a soapy solution to test all gas connections. If a leak is present bubbles will form at the leak
point. When finished remove any residue with a rag. Prevent any soapy solution from coming in
CAUTION
contact with electrical components.
Continue to "BURNER MEDIA INSTALLATION" on page 36.