Chapter 2 Preparations
(2)
Installation procedure
Mount the server to a rack in the following procedure. Always install the server with two or more persons.
1.
Pull the slide rails from left and right outer rails
until they are locked.
2.
With two or more persons, firmly hold the
server and mount it to the rack.
3.
When the server is pushed into the rack
and is locked, push the server to the end
while pulling the release levers (blue) on
both sides of the server.
4.
Push the server until its lock on front
panel clicks.
132
Note
Make sure that locking mechanism work normally.
Locked state
Express5800/R120d-2E User's Guide
2. Installation and Connection
Locking
mechanism
Release lever