Installation Safety Instructions; Requirements On Datacenter Or Computer Room - Emerson SmartCabinet User Manual

Table of Contents

Advertisement

12
Chapter 2 Preliminary Before Installation

2.5 Installation Safety Instructions

The installation safety instructions of the SmartCabinet are as follows:
1. Close all the doors when lifting the equipment by an electrical forklift;
2. Before installation, ensure that the installing site is plane;
3. Switch off the power during the installation. Operation on electrified equipment is forbidden. The connecting cable
must comply with related requirements;
4. Pay attention to the installation requirements of the indoor and outdoor unit when installing the AC.

2.6 Requirements On Datacenter Or Computer Room

Environment
The installation site of the SmartCabinet should be far away from any source of heat and sparkle. Avoid direct
sunlight. The computer room should be free of corrosive gas and organic solvent.
Clearance
When installation, maintain sufficient clearance to facilitate installation and maintenance of the cabinet. The distance
from the front / rear door to the wall or other obstacles must be larger than 1.0m. The required clearance for opening
the front and rear door is shown in Figure 2-13.
90
Rear door
600
Figure 2-13 Required clearance for opening the front and rear door (Top view, unit: mm)
Weight-bearing capacity
After user equipment is installed, the SmartCabinet is heavy, so you should consider the weight-bearing capacity of
the floor of the computer room. The cabinet body of SmartCabinet is 300kg, occupying 0.72m
engineering installation, you need to estimate the weight-bearing capacity of the floor according to the total weight
including the installed equipment. If you cannot estimate the weight-bearing capacity, please consult the nearest
Emerson office or customer service center.
SmartCabinet Integrated Solution User Manual
600
Front door
90
2
. During actual

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents