Dual Cycle Refrigerated Air Conditioning Unit; Ductwork; Site; Customer Hand Over - BONAIRE Installation Instructions Manual

3 & 4 star ducted gas central heater
Hide thumbs Also See for BONAIRE:
Table of Contents

Advertisement

21
Commissioning Check List (cont)
Combustion air meets requirements (internal, under floor).
Fan speed settings are correct.
Burner pressure is correct.
Mounting pad/platform complies with requirements / codes.
Internal unit access platforms & service light fitted and complies with codes.

DUAL CYCLE REFRIGERATED AIR CONDITIONING UNIT

Unit Foundation correct and Condenser unit is level
Leak test performed
System vacuumed down
Condenser service valves opened.
System is charged with additional charge as required
All clearances around the condenser set to manufacturer's specifications.

DUCTWORK

All ductwork is completed to plan, correctly supported and airtight, with no bend
less than 1.5 x the ductwork diameter.
Air distribution checked, dampers are adjusted and all outlets correctly adjusted
and wiped clean.
All roof penetrations are fully sealed and watertight.
Service access cover replaced.

SITE

All rubbish has been removed from inside and on the roof.

CUSTOMER HAND OVER

The following has been explained to the customer –
The operation of the Controller.
The need to open windows and doors for the correct operation of Ducted
Evaporative Air Conditioning
The operation of the bleed or dumping system and it's importance to operate all
the time while ducted Evaporative cooling is in use.
Maintenance requirements
26
Part 5442225 issue E