Commissioning Check List

GENERAL
All equipment ordered by the customer is installed.
The unit is level and secure.
The mains and control wiring are complete, the circuit breaker and GPO are
turned ON.
All Controller functions for the appliance operate.
All electrical or gas connections are to manufacturer's specifications and the
relevant electrical or gas standards and codes.

DUCTED EVAPORATIVE AIR CONDITIONER UNIT

The water supply line has been flushed to clear swarf and debris and is free of
leaks.
The tank is free of foreign matter and debris and the water isolating tap is
turned ON.
Water drainpipe work is completed and sealed.
The water basin fills with water and the float valve closes correctly when the
water level is 65-70mm below the overflow level.
The water pump operates correctly when turned ON at the controller.
The Dialflo water bleed rate is adjusted to suit local water conditions – if
required.
The tank drains correctly when unit turns off.
The fan deck is correctly located and the fan blade spins freely.
The fan operates through the entire speed range.
The minimum & maximum fan speeds is correctly set.
Water distribution is even with the filter pads fitted and the air conditioner
operating pump and fan.

DUCTED CENTRAL HEATING UNIT

Electrical polarity of the power outlet is correct.
Heater is installed away from sources of dust and fumes (i.e. pool
chlorine/petrol etc).
Checked for gas leaks, none present.
Flue outlet pipe complies with limits given / code and is sealed waterproof.
25