1
1
Use four M4x8 pan-head screws to loosely fasten the hood to each of the two side cable management
Step 6
assemblies as shown in
Tighten each of the four screws that fasten the hood to the chassis to 95 to 130 N m (11 to 15 in-lbs).
Step 7
Tighten each of the four screws that fasten the hood to the cable management assemblies to 95 to 130
Step 8
N m (11 to 15 in-lbs).
Tighten each of the 18 screws that fasten the upper and lower cable management assemblies to the
Step 9
rack-mount brackets to 95 to 130 N m (11 to 15 in-lbs).

Installing the Front Door and Air Intake Frame

If you need to install the optional double-hinged door and air intake frame, you must install them after
installing the cable management assemblies on the chassis.
For the double-hinged door to easily open or close in either direction, make sure that the chassis is level.
Note
If necessary, remove the chassis from the rack and adjust the bottom-support rails so that the chassis is
level. Also, make sure that the cable management assemblies are aligned to the vertical sides of the
chassis and that the cable management hood is level when you install those components.
OL-18634-01
Fastening the Top Hood to the Chassis and Cable Management Assemblies
2
Four M4x8 pan-head screws that fasten
the hood to the chassis.
Figure
1
2
Four M4x8 pan-head screws that fasten the hood to
the left and right cable management assemblies.
3-11.
Cisco Nexus 7000 Series Hardware Installation and Reference Guide
Installing the Front Door and Air Intake Frame
2
3-19

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents