Power up and test


Ensure the mains plug is fitted with a 3A fuse.

Switch on

 Power up the system by inserting the mains plug.
 Wait 30 seconds for the system power up routine to be complete.
Check that the vital activity LED is flashing. This is the top led of the four LEDs in the CCU
MDF area.
 Check the Power led is lighting. This is the third led in the CCU MDF area
 Check the DSP led is flashing. This is the fourth led in the CCU MDF area.

Commissioning

1. Remove any anti-scratch protective film from Feature phone LCD's.
2. Label up all Feature phones and other telephones.
3. Ensure that all Feature phones provide dialling tone, ringing and hands free (loud
speaking) facilities. Check that the display is not showing corrupt information.
4. Reset the system to default.
5. Check that all other telephones are connected. Make sure all these phones ring and that
you can dial from them.