10. COMMISSIONING, USE AND TURNING OFF THE BOILER
10.1. Commissioning, Filling Water into Boiler and Heater Installation
- First of all, the electrical connection of the boiler is done. The electrical connection of the device must be
connected to a grounded power supply line that can supply enough voltage (230 VAC, 50 Hz) for the device.
- All radiator valves should be opened.
- CH flow and CH return of boiler should be opened. Check them.
- After all these processes, filling valve is slowly opened and filling procedure is initiated.
The filling process continues until the water pressure of 1.5-2 bar is seen on the LCD display and then the filling
valve is closed.
- When the water pressure increase to 0.8 bar, the LCD will show "AP" and the boiler will switch to automatic
air vent mode. In this case you should definitely wait for 160 seconds without pressing "RESET".
- Check water pressure on pressure indicator frequently and ensure that the pressure is between 1.5 and 2
bar when system is cold. If the pressure drops frequently, it means that there is a water leak in the system. In
such case, it is necessary to call a plumber.
HM Model
ATTENTION : Always close the water filling valve, the installation water may leak and damage
the environment.
- To discharge air out of CH installation, purgers of the radiator is loosened and air is discharged until water
comes out of radiators. This procedure is done for all radiators.
- Pressure is checked again on LCD screen. The filling valve is opened and again pressure is raised to 1.5 - 2
bar level.
- Radiator purgers are checked again to see if there is any air left inside of heating installation. For full efficient
heating, all air must be discharged.
- Finally, check for any leaks in the radiator and piping.
ATTENTION: In order to prevent calcification of the heat exchanger, you are advised not to use
well water, natural spring water instead of mains water.
− Check the domestic water installation by opening the hot water tap. Check for any leaks in the plumbing
pipes.
− The flue group must be assembled from original parts in accordance with the instructions.
− The gas line must be checked and open by the authorized gas company. After all these procedures are
completed, the authorized service must be called to put the device into operation.
− The first start-up of the device must be done by an authorized service.
− At the end of the first operation of the device after its installation, ask the authorized service for information
about the operation of the device and safety devices.
HCH Model
21
HST Model
Need help?
Do you have a question about the CALORA PREMIX and is the answer not in the manual?