BURNER CONNECTION TO THE BOILER

HEAD UNIT ASSEMBLY
• Adjust the position of the coupling flange (19) by loosening the
screws (6) so that the burner head enters the furnace to the extent
recommended by the generator manufacturer.
• Position the insulating gasket (13) on the sleeve, by inserting the
cord (2) between the flange and the gasket.
• Fasten the head unit to the boiler(1) by means of the stud bolts,
washers and the nuts provided (7).
DANGER / ATTENTION
Seal the space between the burner sleeve and the hold on the
refractory material inside the boiler door completely with suitable
material.
ASSEMBLING THE GAS TRAIN
There are different ways of assembling the valve train, as shown in
drawing 0002937060.
Choose the most rational position for the set-up of the boiler room and
the position in which the gas pipeline arrives.
DANGER / ATTENTION
In case of very large valves, e.g. DN65 or DN80, make sure
there is a suitable support to prevent excessive stress on the
gas train fitting.
ASSEMBLY OF VENTILATION SYSTEM
Position the half-hinge on the burner scroll in line with those on the
combustion head assembly.
• Insert the hinge pin (10) in the position considered most suitable
• Connect the cables (switch on and ionisation) to the corresponding
electrodes, close the hinge, locking the burner by means of screws
(11).
COMPLETING BURNER SETUP
• Remove the protective (yellow) caps from the fittings placed beneath
the head unit and near the solenoid valves.
• Connect the light oil pipes (24) provided with the burner to their cor-
responding connectors, making sure they are properly sealed.
11 / 52