Figure 5-2 Floor-mounted installation dimensions
Procedure
Step 1 Align the floor support with the wall surface and keep the support 10 mm to 15
mm away from the wall surface. Level the hole positions using a level, and mark
the hole positions for installing the floor support using a marker. Align the
marking-off template with the surface of the floor mounting kit, determine the
drilling hole positions on the wall for securing the power control module, and
mark the positions using a marker.
Step 2 Install the floor support.
When drilling holes, avoid the water pipes and power cables buried in the wall.
Issue 15 (2024-01-12)
D ANGER
NO TE
M6x60 expansion bolts delivered with the battery are used to install the floor support and
power control module. If the length and quantity of the bolts do not meet installation
requirements, prepare M6 stainless steel expansion bolts by yourself. The expansion bolts
delivered with the battery are mainly used for solid concrete walls and concrete floors. If
other types of walls and floors are used, ensure that the walls and floors meet the load-
bearing requirements (one battery expansion module weighs 50 kg) and select the bolts by
yourself.
Copyright © Huawei Digital Power Technologies Co., Ltd.
5 System Installation
69

Advertisement

Table of Contents
loading

This manual is also suitable for:

Luna2000-30-s0

Table of Contents