Viewing The Plant Creation Status - Huawei SUN2000-8K-LC0 Series User Manual

Hide thumbs Also See for SUN2000-8K-LC0 Series:
Table of Contents

Advertisement

SUN2000-(8K, 10K)-LC0 Series
User Manual
Table 7-3 DRM requirements
Mode
DRM0
Procedure
Step 1 On the home page, choose Settings > Feature parameters.
Step 2 Set DRM to
Figure 7-8 DRM
----End

7.4 Viewing the Plant Creation Status

The FusionSolar app provides an overview of plants. You can view the plant
running status, energy yield and consumption, revenue, and energy flow diagram
in real time.
Issue 01 (2023-09-15)
NO TE
The demand response enabling device (DRED) is a power grid dispatch device.
Port on the Inverter
DI1 and GND of the COM
port
.
Copyright © Huawei Digital Power Technologies Co., Ltd.
7 Power-On and Commissioning
Requirements
● When S0 and S9 are switched
on, the inverter should be shut
down.
● When S0 is switched off and
S9 is switched on, the inverter
should be connected to the
power grid.
87

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sun2000-10k-lc0 seriesSun2000-8k-lc0Sun2000-10k-lc0Sun2000-8k-lc0-zhSun2000-10k-lc0-zh

Table of Contents