Commissioning

OTHER EXTERNAL WIRING

Refer to the appropriate module wiring instructions to identify the terminals for cable connections.
Commissioning the external wiring comprises the following main steps:
01
Check the module external wiring for continuity, short circuits and open circuits.
02
Connect the external wiring to the panel.
03
Check for faults after the external wiring is connected to the powered-up panel. Rectify the indicated faults by
using the probable solution guidance.
You will need Access level 3 controls at the panel for which you will need a pass-code PIN "33", which is the
current default PIN. Note during commissioning the Access level 3 pass-code PIN may have been changed to
a unique 4 digit PIN for additional security.
04
Repeat this process for the next module until all the modules are recognised by the panel and are working fault
free.
TEMPORARY PROCEDURE FOR POWERING UP AN INSPIRE NETWORK
When powering up a network of INSPIRE panels and to prevent 'Subsystem initialization' fault being displayed on
Master panel (usually panel 1) you must follow this sequence:
Turn on the power to Master panel and then Slave panel(s) in this sequence only.