Installation, commissioning and operating flowchart

Identify the frame size of your drive, R7 or R8.
Plan the installation.
Check the ambient conditions, ratings, required
cooling air flow, input power connection,
compatibility of the motor, motor connection,
and other technical data.
Select the cables.
Unpack and check the units.
Check that all necessary optional modules and
equipment are present and correct.
Only intact units may be started up.
Check the installation site.
If the drive is about to be connected to an IT
(ungrounded) system, check that the drive is not
equipped with EMC filter +E202.
Note: You cannot disconnect the EMC filter.
Route the cables.
Check the insulation of the motor and the motor
cable.
Install the drive. Connect the power cables.
Connect the control and the auxiliary control
cables.
Commission the drive.
Task
Introduction to this manual 19
Technical data
(page 99)
Technical data
(page 99)
Planning the electrical installation
Option manual (if optional equipment is included)
Unpacking the unit
(page 33)
If the converter has been non-operational for more
than one year, the converter DC link capacitors
need to be reformed.
Capacitors
(page 95)
Before installation
(page 34)
Technical data
(page 99)
Type code
(page 27)
Routing the cables
(page 62)
For compliance with the European Union EMC
CE marking
Directive, see
Checking the insulation of the assembly
Electrical installation
(page 63),
Resistor braking
(page 131) (optional)
Appropriate firmware manual
See
(page 37)
(page 125)
(page 63)