4 INSTALLATION
6. Position the deflection unit on the installation surface of the collimator bracket using the pins.
7. Secure the deflection unit with the screws included in the Collimator Bracket Set.
8. Screw the collimator into the collimator bracket.
9. Connect the fibre of the laser to the collimator according to the collimator manual.
 The deflection unit is aligned to the fibre of the laser.
If the deflection unit has a water cooling option, connect the cooling water to the deflection unit. In
case of water-cooled collimator brackets for example using Collimator Bracket Set 001 it is
recommended to implement the following cooling circuit: chiller flow line - deflection unit inlet -
deflection unit outlet - collimator bracket - chiller return flow. There is no preferred water flow
direction for the collimator bracket. Pay attention to page 31, Requirements for cooling water.
4.7

Completing installation

1. Make sure that the control signals and the power supply correspond to the relevant specifications.
2. Check whether the connections for the control signals and the power supply are correctly wired
(see page 26, Interfaces).
3. Connect the plug connections when not connected to the voltage.
4. Make sure that the working area is clear and there are no reflective materials in it.
© 2022 RAYLASE GmbH SUPERSCAN IV
MN105-en / v1.0.12
35

Advertisement

Table of Contents
loading

This manual is also suitable for:

Superscan iv-15Superscan iv-20Superscan iv-30

Table of Contents