Section 9
Testing functionality by secondary injection
9.17
Exit test mode
The following procedure is used to return to normal operation.
1.
Navigate to the test mode folder.
2.
Change the On setting to Off. Press the 'E' key and the left arrow key.
3.
Answer YES, press the 'E' key and exit the menus.
152
After exiting the IED test mode, make sure that the MU is returned to normal mode.
© 2017 - 2022 Hitachi Energy. All rights reserved
1MRK 505 395-UEN Rev. G
SEMOD53244-3 v6
Line differential protection RED650
Commissioning manual