To verify the settings in the most common back-up trip mode 1 out of 3, it is sufficient to test phase-
to-earth faults.
At mode 2 out of 4 the phase current setting, IP> can be checked by single-phase injection where the
return current is connected to the summated current input. The value of residual (earth fault) current
IN set lower than IN> is easiest checked in back-up trip mode 1 out of 4.
9.5.6.1

Function revision history

Document
revision
A
B
C
D
E
9.5.6.2
Checking the phase current operate value, IP>
The check of the IP> current level is best made in FunctionMode = Current and BuTripMode = 1 out
of 3 or 2 out of 4.
1.
Apply the fault condition, including START of CCRBRF, with a current below the set IP>.
2.
Repeat the fault condition and increase the current in steps until a trip occurs. Note that the
START signal shall be re-applied for each new current value.
3.
Compare the result with the set IP>.
9.5.6.3
Checking the residual (earth fault) current operate value IN> set below IP>
Check the low set IN> current where setting FunctionMode = Current and setting BuTripMode = 1 out
of 4
1.
Apply the fault condition, including START of CCRBRF, with a current just below set IN>.
2.
Repeat the fault condition and increase the current in steps until trip appears. Note that the
START signal shall be re-applied for each new current value.
3.
Compare the result with the set IN>.
4.
Disconnect AC and START input signals.
9.5.6.4

Checking the re-trip and back-up times

The check of the set times can be made in connection with the check of operate values above.
Choose the applicable function and trip mode, such as FunctionMode = Current and RetripMode =
UseFunctionMode.
1.
Apply the fault condition, including start of CCRBRF, well above the set current value. Measure
the time from START of CCRBRF.
2.
Check the re-trip t1 and back-up trip times t2 and t3.
Line differential protection RED650
Commissioning manual
Product
History
revision
2.2.1
I>BlkCBPos setting functionality correction.
2.2.1
-
2.2.1
-
2.2.4
-
2.2.5
-
If No CBPos Check or Retrip off is set, only back-up trip can be used to check set
IP>.
© 2017 - 2022 Hitachi Energy. All rights reserved
Section 9
Testing functionality by secondary injection
GUID-3A043295-3AE3-437E-BBE9-D7FD6F349892 v2
M12104-23 v14
M12104-80 v10
M12104-93 v12