Resetting The Temperature Limiter; Technical Specifications - Nibe EMINENT-E/CU/R 35 Installation Instructions Manual

Hide thumbs Also See for EMINENT-E/CU/R 35:
Table of Contents

Advertisement

Available languages

Available languages

GB
Emptying
Emptying takes place through the safety valve's overflow
pipe and is done as follows:
1
Switch off the power to the water heater.
2
Close the shutoff/non-return valve by turning
the knob (22) clockwise until it bottoms.
3
Turn the mixing valve's knob (25) anticlockwise
to the maximum position.
4
Open the safety valve by turning the knob (23)
slowly anticlockwise a quarter turn until it re-
mains in the raised position.
NOTE! Water may splash by the overflow pipe.
5
Remove the venting screw (45) and open the
lowest placed hot water tap on the pipe system.
NOTE! Water may splash out of the venting
screw hole and could be hot.
Compressed air can be applied through the venting
screw hole to increase the emptying speed.
Maintain the position of the valves after the above ac-
tions until the water heater is to be used again.
NOTE! The overflow pipe must be connected to
pos (43).
25
42
41
43

Technical specifications

Volume
Max workingpressure
Voltage
Enclosure class
Output
Fuses required at 1/3 kW
Heating time to 45 °C at 1/3 kW*
Heating time to 80°C at 1/3 kW*
Net weight E/CU/R
Sacrificial anode EMINENT-E
Corrosion protection EMINENT-E
Corrosion protection EMINENT-CU
Corrosion protection EMINENT-R
* With incoming cold water of 10 °C.
12
45
22
(litres)
(MPa/bar)
(kW)
(A)
(hours)
(hours)
(kg)
(mm)
EMINENT-E/CU/R 35, 55, 100
Actions with operating disruptions
Check the installation's fuses and the setting of the ther-
mostat and mixing valve.
Wait a few hours without tapping any hot water and
then check whether the temperature level has risen. If
there is still no hot water, contact the installation engi-
neer.

Resetting the temperature limiter

The temperature limiter is situated under the plastic co-
ver (2) and is reset by pressing the button see the figure.
NOTE! All work in the electrical connection area must
be carried out under the supervision of a qualified elec-
trician.
L E
K
Service
23
Contact the main contractor when a service is necessary.
You must then state the serial number (95) 14 digits.
IP 24
PED 97/23/EC
35
230 VAC + PE/2 x 400 VAC + PE
1,4/0,5
2,9/1,0
19/21/17
165
55
100
0,9/9
IP 24
1/3
6/10
2,3/0,8
4,1/1,4
4,5/1,5
8,1/2,7
25/28/22
36/40/31
280
435
Enamel
Copper
Stainless

Advertisement

Table of Contents
loading

This manual is also suitable for:

Eminent-e/cu/r 55Eminent-e/cu/r 100

Table of Contents