5.3 Mechanical installation

WARNING
Incorrect installation and start-up
Improper performance of work can lead to serious injuries and damage to property.
Work may only be carried out by trained specialist personnel.
Meet all safety requirements before installation.
Only carry out mechanical installation in a de-energized state.
Provide sufficient free space for the installation. The installation site must be sufficiently
accessible so that the charging system can be installed and serviced without interference.
The installation site must be chosen so that the cables of the cable management system do
not protrude onto the road and do not come to rest between the kerb and the road.
Use a suitable lifting tool with sufficient load capacity during installation.
NOTE
The use of specific installation materials for the charging system may be necessary depending on the
condition of the ground or special local conditions. The necessity must be considered individually at
each location.
The following description of installation with specific installation material is exemplary. Local
conditions are not dealt with in detail. Deviating procedures may only be initiated by competent
persons.
NOTE
To protect the charging system, we recommend to install an approach limiter (e.g. bollard).
2023-02
A11XCXXXXX | 02
23

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the ADVANCED IMS bm SAM and is the answer not in the manual?

This manual is also suitable for:

Duo ims samDuo fleet ims sam

Table of Contents