Figure 3-1 Positions of the corner fittings of the unit
When marking the positions for corner fittings, ensure that the four lines form a
rectangle.
Step 4 Place the shock absorption pads at the corresponding positions of corner fittings
on the concrete platforms.
Step 5 Adjust the unit in the required direction, connect the steel hoisting ropes, and
hoist the unit onto the concrete platforms.
● When hoisting the unit, ensure that the four corner fittings of the unit are
aligned with the marked mounting positions for corner fittings on the concrete
platforms.
● When hoisting the unit, prevent the unit from being scratched by steel ropes.