1.3 Environmental Requirements

If the equipment room has a load rate less than or equal to 30% or is not properly
sealed, the humidity in the equipment room may be too high or too low. This is
not a product quality issue. It is recommended that a constant humidity machine
be installed in the equipment room.
Table 1-1 Installation requirements
Item
Transportation passage
Foundation
Water supply
Issue 03 (2022-11-25)
Do not stack whole units together.
Before installing a rainproof canopy, ensure that the protective cloth at the air
exhaust vent is sealed. Before installing the air supply and return ducts,
ensure that the protective cloth at the vents is sealed.
NO TICE
Copyright © Huawei Digital Power Technologies Co., Ltd.
Specifications
Width: > 3000 mm, height: > 4000 mm
Bearing capacity of each support point: > 1120 kg (six
support points)
Equivalent uniformly distributed load: ≥ 600 kg/m
● It is recommended that a water pressure gauge
and a manual ball valve be installed on the
external water refill pipe of the unit so that the
water supply pressure can be easily adjusted and
the water refill pipe can be maintained individually
for the unit.
● The water supply pressure must range from 0.1
MPa to 0.7 MPa.
● Water quality requirements of the unit:
– Turbidity ≤ 5 NTU
– 6.5 ≤ PH (25°C) ≤ 8.5
– Total hardness ≤ 100 mg/L
– Total alkalinity ≤ 200 mg/L
– Chlorine ion ≤ 150 mg/L
– COD ≤ 30 mg/L
– Conductivity < 600 μS/cm
CAUTION
If the water quality of the unit does not meet the
requirements, reduce the concentration times. Drain
the water if the conductivity of circulating water in
the water tank of the unit exceeds 1800 μS/cm.