CABIN TEMPERATURE CONTROL - ADJUSTMENT/TEST
1.
I
NTRODUCTION
A.
Purpose
The following procedure provides instructions for verifying proper operation of the cabin
temperature control system.
NOTE: The following test procedure requires qualified operators using approved aircraft
operational procedures.
B.
Equipment and Facilities Required
(1)
Equipment
(2)
Facilities
2.
T
S
-
EST
ET
UP
A.
Verify that all circuit breakers are closed on all circuit breaker panels, except those necessary for
ground safety.
B.
Verify that all equipment necessary for the test is installed in the aircraft before proceeding.
3.
T
EST
A.
Test the cabin temperature control system in accordance with Bombardier Completion Center
Ground Test Procedure, document number TE-GTP-187, revision (B), or the latest approved
revision.
4.
T
C
EST
OMPLETION
A.
Disengage aircraft electrical buses and ECS system.
B.
Shut down APU unless required for further testing.
C.
Remove all equipment used for these tasks and return aircraft to its initial condition.
TE-55965000-SMM
EFFECTIVITY:
Revision A
CL-604 SUPPLEMENTAL MAINTENANCE MANUAL
None
None
21-61-18
Page 501
Nov 10/2006