Download Print this page

Introduction; Test Set-Up; Test; Test Completion - BOMBARDIER Chalenger 604 Supplemental Maintenance Manual

Advertisement

1.
I
NTRODUCTION
A.
Purpose
The following procedure provides instructions for verifying proper operation of the entry area
heater system.
NOTE: The following test procedure requires qualified operators using approved aircraft
operational procedures.
B.
Equipment and Facilities Required
(1)
Equipment
(2)
Facilities
2.
T
S
-
EST
ET
UP
A.
Start APU or aircraft engines.
B.
Verify that system circuit breaker(s) are closed.
3.
T
EST
A.
Test the entry area heaters in accordance with Bombardier Completion Center Cabin Management
System Ground Test Procedure, document number TE-GTP-251, revision (F), or the latest
approved revision.
4.
T
C
EST
OMPLETION
A.
Shut down engines or APU.
B.
Remove all equipment used for these tasks and return aircraft to its initial condition.
TE-55965000-SMM
EFFECTIVITY:
Revision A
CL-604 SUPPLEMENTAL MAINTENANCE MANUAL
ENTRY AREA HEAT - ADJUSTMENT/TEST
None
None
21-40-03
Page 501
Nov 10/2006

Hide quick links:

Advertisement

loading

This manual is also suitable for:

Cl-600-2b16