Table 8: Site Preparation Checklist for SSR1400 Installation
Item or Task
Plan the rack location,
including required space
clearances.
Secure the rack to the floor
and building structure.
Cables
•
Acquire cables and
connectors.
•
Review the maximum
distance allowed for each
cable. Choose the length
of cable based on the
distance between the
hardware components
being connected.
•
Plan the cable routing and
management.
SSR1400 Site Guidelines and Requirements
IN THIS SECTION
General Site Installation Guidelines | 17
Site Electrical Wiring Guidelines | 17
Environmental Requirements and Specifications for SSR1400 | 19
Clearance Requirements for Hardware Maintenance of SSR1400 | 19
Additional Information
"Clearance Requirements for Hardware Maintenance of SSR1400" on page 19
(Continued)
16