Commissioning

8 Commissioning
NOTE
Observe qualifications.
Commissioning must be performed only by qualified electricians!
It is essential to follow the procedure described below!

8.1 Configuring the components

8.1.1 Network overview

Operating
mode
EMS
SRC1420
preconfigured
SRC4310
preconfigured
Inverter
preconfigured
SRC1420
Master
SRC4310
preconfigured
Inverter
preconfigured
SRC1420
Factory
reset
SRC4310
Inverter
Version:1.3
IP addresses
LAN
WAN
DHCP
172.17.10.100
172.17.10.101
172.17.10.200
DHCP
172.17.10.100
172.17.10.101
...
172.17.10.200
1.0.0.1
192.168.0.254
192.168.0.10
Observe inverter instructions
GSS0608
Subnet
Gateway
4G
-
255.255.255.0
DHCP
-
255.255.255.0
DHCP
-
255.255.255.0
192.168.0.10