10 Switching off the system

10.1 Switching off the system before performing
maintenance or decommissioning
NOTE
Observe qualifications.
Maintenance work, service and repairs as well as decommissioning must be
performed by qualified electricians only.
Switch off all fuses belonging to the system. Use a suitable testing device to check that no
voltages are present.
Only work with insulated tools and remove body jewellery to avoid short circuits and electrical
shock.
Never work on the system on your own.
Procedure:
1. Initialise the shut-down process via the controller software.
2. Switch off the backup fuses of the storage system at the connection point and secure them
against being accidentally switched on again, or remove the fuses.
3. Open the two system doors
4. Turn the AC main switch to the OFF position. Wait at least 5 minutes until any residual voltage
has been eliminated.
5. Set the key switch on the SRC4310 to the OFF position. Remove the key to prevent it from being
switched on again.
6. Observe the 5 safety rules and use a suitable testing device to ensure that no voltage is present.
Maintenance and repair work can now begin ( 11 Maintenance & storage)
For complete decommissioning or disassembly of the system, further disassembly steps are described
below ( 10.2 Order of disassembly)
Page 58 of 72
GSS0608
Switching off the system
Version: 1.3