Procedure To Install Site I/O Cable Between Site I/O Junction Box And Site I/O Interface - Motorola SC 300 Manual

Bts hardware installation, atp and fru procedure
Hide thumbs Also See for SC 300:

Advertisement

Site I/O , Span Line, RGPS and Modem Cabling for Sites Equipped With
Customer–Supplied Site I/O Interface
Procedure to Install Site I/O
Cable Between Site I/O
Junction Box and Site I/O
Interface
Figure 4-15: Site I/O Cabling Details (MicroCell Unit Shown)
SITE I/O
JUNCTION BOX
DEC 2000
SC 300 BTS Hardware Installation, ATP and FRU Procedures
– continued
Route the Site I/O junction box cable from the unit location(s) to the Site
I/O Extender Cable (cable Z). Route cable Z to the Site I/O interface.
Connect the appropriate connectors within the Site I/O interface. Refer
to Figure 4-15 and Table 4-25.
If lightning arrestors are required, they must be customer–supplied.
Lightning arrestors are not necessary for sites equipped with optional
Primary Surge Suppressor.
RGPS
M
SITE I/O
INTERFACE
Z
SITE I/O
DEUTSCH
CABLE
CONNECTOR
N
SPAN
CUSTOMER
O
INPUTS
V
PHONE(MODEM)
PRELIMINARY
4
4-25