Agitation Before Resuming a Spray Job (i-version)

If a spray job has been interrupted for a while, severe sedimentation may occur depending on the chemicals being used.
Before resuming the spray job, it might be necessary to agitate sediment material.
1. Press
to turn the suction valve towards "Suction from main
tank".
2. Press
to turn the pressure SmartValve towards "Pressure
draining/(TurboFiller)".
3. Press
to turn On the agitation valve.
DANGER! Before pressing
the quick coupler lid is correct and completely fitted to the filling
stud into its locked position. Failure to do so may cause risk of
contamination and injury from quick coupler lid being "shot" off
when pressurized! If not possible to fit the lid completely,
lubricate the rubber seal and the grip hooks.
4. Engage the pump and set PTO speed to max. 540 RPM or 1000 RPM (depending on pump model).
5. Agitation has started and should be continued for at least 10 minutes.
6. The spray job can now be resumed. Press
SmartValve towards "Spraying" and start spraying.

Before Returning to Refill the Sprayer

If the sprayer is to be refilled at the farm, or at a fixed filling place without a filling space with hard surface and drain to a
closed reservoir, the sprayer should be rinsed before returning to refill.
Dilute the residues of the spraying circuit, and spray it on the crop. Depending on the weather conditions, it could also be
necessary to clean the sprayer on the outside now while in the field, before returning to the farm.
±
WARNING! Always follow local legislation in force at any time.
, it is very important to be sure that
to turn pressure
5 - Operation
117

Advertisement

Table of Contents
loading

Table of Contents