Repair
Cooling system
Installation
u Insert o-ring 7 and flange 6 on pipe from oil cooler casing.
u Mount pipe 14 with o-rings 3 on flange 6.
u Mount coolant pipeline 13 with o-ring 7 on flange 6.
u Insert guiding rods in coolant pump 9.
u Insert o-rings 10, 11, 12.
u Insert coolant pump HT 9.
u Tighten screws 1, 16 according to tightening specifications.
u Remove guiding rods.
u Tighten remaining screws 16 to torque.
u Assemble t-pipe 2, pipe 4 and flange 6 with o-rings 3, 7, 17.
u Position assembly with screws 1, 5 and tighten according to tightening specifications.
u Install test point fitting 8 on coolant pump.
Information
Vent coolant circuit at the end of installation.
Specific values
Not applicable.
Tightening specifications
Refer to standard tightening torques.
page 264.)
3.10.6 Coolant pump LT removal and installation (SL 215)
Previous tasks
q Drain LT coolant circuit.
q Remove machinery LT cooling system piping.
q Remove vibration damper cover.
removal and installation, page 59.)
q Remove battery charging alternator cover.
alternator & PTO cover removal and installation, page 61.)
Specific safety instructions
NOTICE
Risk of property damage by reuse of sealing.
Leakage by faulty seal.
u Replace all sealings.
222
(For more information see: 5.3 Standard tightening torques,
(For more information see: 3.2.1 Vibration damper cover
.
(For more information see: 3.2.2 Battery charging